How Long Does a Kitchen Renovation Actually Take? A Timeline Guide

One of the things that holds many homeowners back from starting a kitchen renovation is not the cost, or even the decision-making, it is the uncertainty. How long will it actually take? What happens at each stage? Will my kitchen be out of action for weeks?
At Kitchen Living, we work with homeowners across Hampshire and know that feeling confident about the process makes all the difference. Here is a clear, honest guide to what the kitchen renovation journey looks like, from your very first conversation with us to the moment you cook your first meal in your new kitchen.
You can also read our more detailed page on your kitchen renovation timeline for a full stage-by-stage breakdown.

Stage 1: The Initial Showroom Consultation
Typical timeframe: Week 1
Everything starts with a visit to our Hedge End showroom, just a ten-minute drive from Southampton city centre. Our designers will ask questions about how you use your kitchen, what you love and do not love about your current one, your style preferences, and your rough budget. You will leave with a feel for the process, some inspiration, and a clearer sense of what is possible for your home.
Stage 2: The Home Measure
Typical timeframe: Weeks 2–3
Once you are ready to move forward, one of our designers will visit your home to take precise measurements of your kitchen space. This is also a chance to assess the room in context, where the natural light falls, how the space connects to the rest of the house, and any structural considerations that might affect the design.

Stage 3: The Design Presentation
Typical timeframe: Weeks 4–5
With your measurements and brief in hand, our designers create your bespoke kitchen design using advanced CAD software. You will then be invited back to our showroom for a full design presentation, complete with a transparent, itemised quotation. Everything is laid out clearly so you know exactly what you are getting and what it costs.
Stage 4: Review, Revisions, and Sign-Off
Typical timeframe: Weeks 5–8 (at your own pace)
Take as long as you need to review the design, discuss it with your household, and come back to us with any changes or questions. There are no extra charges for revisions and no hard sell. Once you are satisfied and ready to proceed, you will confirm your order and a deposit will be taken to begin manufacturing.
Stage 5: Manufacturing Your Bespoke Kitchen
Typical timeframe: 8–12 weeks after order
Because all of our kitchens are bespoke and made to order, the doors, units, and components are specially crafted to your exact specifications. This manufacturing period is typically around eight to twelve weeks, depending on the complexity of your design and the finishes chosen. If your project involves any preparatory building work, knocking down a wall, moving a radiator, updating electrics, this is the ideal window to get that underway.

Stage 6: Installation
Typical timeframe: 1–2 weeks on site
When your kitchen arrives, our in-house installation team takes care of everything. Because we design, supply, and install under one roof, there is no disconnect between what was planned and what gets fitted. Most installations take between one and two weeks on site. We will give you a clear schedule before work begins so you can plan around it.
Stage 7: Final Snagging and Sign-Off
Typical timeframe: Shortly after installation
Before we consider the job complete, we carry out a thorough check of every detail, from the alignment of doors and drawers to the finish on every surface. If anything is not quite right, we put it right.

The Full Timeline at a Glance
| Stage | What Happens | Timeframe |
|---|---|---|
| 1. Showroom consultation | Meet the team, explore the showroom | Week 1 |
| 2. Home measure | Designer visits your home | Weeks 2–3 |
| 3. Design presentation | CAD design and quotation revealed | Weeks 4–5 |
| 4. Revisions & sign-off | Changes made at your pace, order confirmed | Weeks 5–8 |
| 5. Manufacturing | Bespoke kitchen crafted to order | 8–12 weeks |
| 6. Installation | Fitted by our in-house team | 1–2 weeks on site |
| 7. Final snagging | Full check and sign-off | Shortly after |
From your first showroom visit to your finished kitchen, the full process typically takes around four to five months, though this can vary depending on how quickly you want to move through the design stages.
Ready to Start Your Kitchen Journey?
If you are based in Hampshire and thinking about a new kitchen, our team is here to guide you through every step. Book a design appointment at our Hedge End showroom, browse our completed kitchen projects for inspiration, or simply get in touch for a no-obligation chat.

Frequently Asked Questions
How long does the full kitchen renovation process take?
From your first showroom visit to your finished kitchen, the process usually takes around four to five months. This can vary depending on the design, manufacturing timescales, and how quickly decisions are made.
What is the lead time for a bespoke kitchen?
Lead times for bespoke cabinetry and appliances are typically between eight and twelve weeks from the point of order. This is the manufacturing time - your kitchen is being made to your exact specification during this period.
How long will I be without a working kitchen during the renovation?
The period of maximum disruption is typically the installation phase, which usually lasts one to two weeks for a standard project. Having a temporary setup: microwave, kettle, and access to running water - makes the disruption considerably more manageable.
Can I take my time deciding on the design?
Yes. The timeline moves at your pace through the design and revision stages. Some clients are ready to sign off quickly, while others prefer more time to review finishes, layouts, and details before committing.
When should I start planning my kitchen renovation?
If you have a target completion date, work backwards by at least five months to allow sufficient time for the design process, manufacturing lead times, and installation. Starting earlier than you think you need to is almost always better than leaving it too late.